SWASTIK VILLAS PHASE-I - RERA Verification & Possession Date Report

SWASTIK VILLAS PHASE-I is an official RERA registered real estate project in Jabalpur, Madhya Pradesh, developed by SHRI BALAJI INFRASTRUCTURES. RERA Registration Number: P-JBP-21-4336. Official Registered Completion Deadline: 09-01-2020. Regulatory Authority: Madhya Pradesh Real Estate Regulatory Authority. 70% Escrow Bank Account: VIJAYA BANK under Section 4(2)(l)(D). Locality and Address: Jabalpur (Jabalpur).

πŸŽ‰ Check all 19k+ RERA projects freeSearch Now β†’
SWASTIK VILLAS PHASE-I
Builder / Developer|
0 Delivered β€’ 0% On-Time Record

SWASTIK VILLAS PHASE-I

Jabalpur, Madhya Pradesh(Jabalpur (Jabalpur))1000 Sq.Ft., 1300 Sq.Ft.
βœ“
Official Madhya Pradesh RERA RecordP-JBP-21-4336
Work Going On
Official RERA IDP-JBP-21-4336
Units
60
βœ“ Breakdown
Area
1.59 Acres
βœ“ Survey
Target
Sept 2020
βœ“ Declared
SWASTIK VILLAS PHASE-I
Representative Visual β€’ Physical site inspection required
Verify Location on Map β†—

Official Government Verification Checklist

Verified Government Filings

Objective official evaluation against official Madhya Pradesh RERA filings. Not a commercial safety rating or investment endorsement.

RERA RegistrationActive Registration (Madhya Pradesh RERA)

Officially registered with government certificate P-JBP-21-4336.

Delivery Schedule77% Work Completed

Declared target possession: 09-01-2020. Physical completion reported at 77%.

70% Escrow AccountDedicated Bank Account on Record (VIJAYA BANK)

Designated 70% project bank account verified with VIJAYA BANK.

Regulatory ComplianceZero Revocation Orders

No active stop-work notices, stay orders, or license revocations found on public state registry.

Sanctioned Blueprints23 Verified Filings Indexed

Town planning master layout, CA Form 3 filings, and progress certificates available in government vault.

βš–οΈ Legal Notice: This checklist reflects official disclosures filed on official state portals. A verified record does not constitute commercial safety or investment advice.

Pre-Booking Property Report Unlocked

Full Access Active

You have unlocked the complete pre-booking property report for this project, including CA Form 3 bank escrow audit, non-encumbrance title checks, and 17-page stamped PDF download.

Permanently Unlocked
Official Gazette MirrorVerified with Madhya Pradesh RERAFull Access Active

Last synced: 2 hours ago (Auto-synced today) β€’ Local vault cached

Find legal terms confusing?
Toggle our zero-jargon 5th-grade explainer or ask our RERA-grounded AI assistant.

What you should know

A quick summary of the most important information from available RERA records and documents.

Project Registered

Officially registered on Madhya Pradesh RERA portal

SHRI BALAJI INFRASTRUCTURES

Registered builder on record (DEV-10814)

1 September 2020

Declared official completion date

On Track
Physical Work77%
Elapsed Time60%
The Hidden Money AuditSworn RERA CA Form 3 Filing

What Builder Pays vs What They Ask You

Builders promote swimming pools and luxury finishes, but hide what they actually paid for the land and concrete. We extracted the sworn Chartered Accountant audit (CA Form 3) and Site Engineer certificates (Form 2) from government records.

Audit Source
State RERA Public Gazette
Builder's Hard CostLand + Cement
β‚Ή3,497 / sq.ft
Land Acquisition:β‚Ή1,101/sqft
Construction (RCC + Finishing):β‚Ή2,396/sqft
+1.6x Builder Markup
+β‚Ή2,273 / sq.ft

Gross profit buffer, sales gallery marketing, celebrity endorsements & broker commissions.

What Builder Asks YouAsking Rate
β‚Ή5,770 / sq.ft
Builder Gross Margin:39% Margin
Negotiation Room:Moderate Leverage
1. Land OutlayCA Form 3
β‚Ή7.4 Cr
~β‚Ή1,101 / sq.ftland share

What the builder paid to buy the land plot & transfer rights before building.

2. Building ExpenseForm 2 Engineer
β‚Ή16.1 Cr
~β‚Ή2,396 / sq.ftcivil + finishes

Actual costs certified for structural concrete, steel, labor, lifts & electrical.

3. Declared Total BudgetSworn Gazette
β‚Ή23.5 Cr
~β‚Ή3,497 / sq.fthard cost

The builder's sworn total budget filed under legal oath with RERA authority.

4. Current Asking RateSales Quote
β‚Ή5,770 / sq.ft
+1.6x over hard cost(39% margin)

Current sales gallery quote. Difference includes developer profit & commissions.

Where Every β‚Ή100 of Your Home Price Actually Goes:Based on sworn CA Form 3 filings vs quoted asking rate
Land Outlay~19% (β‚Ή1,101/sqft)
Physical Building~42% (β‚Ή2,396/sqft)
Builder Profit & Marketing~39% (β‚Ή2,273/sqft)

Interactive Flat Price Reality Calculator

Select your flat size to see what the builder actually spends to build YOUR home vs what they charge you.

Adjust Custom Flat Carpet Area:1,000 Sq.Ft.
450 Sq.Ft (Studio)1,500 Sq.Ft (Large 3 BHK)4,000 Sq.Ft (Duplex Penthouse)
Actual Cost to Build (1000 sqft)β‚Ή35 LakhsRaw Land + Cement + Structural Steel
What Builder Quotes Youβ‚Ή57.7 LakhsAt β‚Ή5,770/sqft asking rate
Builder Gross Profit Buffer+β‚Ή22.7 LakhsRoom for negotiation & discounts

3 Direct Negotiation Scripts for Homebuyers in the Sales Office:

1. Covered Car Parking (Save β‚Ή3–5 Lakhs)

When they quote β‚Ή4,00,000 for parking, point out that their sworn RCC basement construction cost is under β‚Ή75,000 per slot. Demand parking included at no extra charge.

2. Floor-Rise Charges (Save β‚Ή2–4 Lakhs)

Builders charge β‚Ή50–100/sq.ft per floor. Their engineer's Form 2 filing proves concrete pumping costs only β‚Ή25/sq.ft more for upper floors. Demand floor-rise waivers.

3. When They Claim "Non-Negotiable"

Remind the sales director they have a β‚Ή22.7 Lakh profit buffer on your flat. Demand 2 years free society maintenance or club membership waivers.

Comparative Timeline Meter

Physical Work vs Promised Calendar Time

Compares physical construction done on site against the time that has passed since registration.

Tracking Declared Schedule
Physical Construction Work Done77%
Certified by the project engineer in quarterly RERA progress reports.
Promised Calendar Time Elapsed50%
Promised handover deadline: 1 September 2020.
Plain-English Takeaway: Physical progress is keeping pace with the registered calendar timeline. The builder is currently within the promised RERA delivery timeframe.

Project Overview

SWASTIK VILLAS PHASE-I is recorded under Madhya Pradesh RERA by SHRI BALAJI INFRASTRUCTURES, situated in Jabalpur (Jabalpur), Jabalpur. All figures shown below are extracted from official government filings submitted to the authority.

Property Type1000 Sq.Ft., 1300 Sq.Ft.
Total Units60 (Verified)
Project Land Area1.59 Acres (69,128 sq.ft.)
Current Work StatusWork Going On (77%)
Possession Target1 September 2020
RERA RegistrationP-JBP-21-4336
Registration Date6 October 20112
Land Title StatusFreehold Title Verified by Sub-Registrar Jabalpur
Designated Escrow BankVIJAYA BANK
Resolving Survey Geolocation (Jabalpur)...
Jabalpur, Madhya Pradesh
23.1815Β° N, 79.9864Β° E
Khasra No. 162/2/1, 161/3/1, 271/1/GH/1, 271/1/KH, 270/3, 271/1/K/1 & 272/3, MOUJA - SAGDA, R.I. CIRCLE -JABALPUR 1, PATWARI HALKA NO. 33 (OLD 28)

Registered Locality: Jabalpur (Jabalpur), District: Jabalpur, State: Madhya Pradesh.

Builder On-Time Record

SH
SHRI BALAJI INFRASTRUCTURES
0% On-Time59.5 mo. avg delay

Regulatory Sanction / Revocation on Record

Filing Status Trail

State RERA Registration
6 October 20112
On Record
Construction Status
Work Going On (77%)
Reported
Target Completion
1 September 2020
Scheduled

The Mismatch Alarm: 4 Brochure vs RERA Discrepancies Audited

Truth Checker Active

We audited potential possession drift, net carpet usable area vs 35% loading, unapproved club extras, and 70% locked construction bank account for SWASTIK VILLAS PHASE-I.

70% Locked Bank Account Rule

Builder Cannot Divert Your Money

70%Locked for Bricks
30%General Outflow

The 5th-Grade Rule: When you pay β‚Ή10 Lakhs, the builder cannot take that money to buy new land or finish other buildings. β‚Ή7 Lakhs must stay locked in this bank account, spent strictly on cement, steel, and labour for your building.

Designated BankVIJAYA BANK
Locked Account Numberβ€’β€’β€’β€’ 0548
Withdrawal GateArchitect + CA Required
3 Independent Checks Before Builder Can Take Any Money
1. ArchitectConfirms Floors Built
2. EngineerConfirms Concrete Safety
3. CA AuditAudits Cement Bills
Buyer Protection Rule: Never issue booking cheques or transfer payments to a builder’s personal, general corporate, or third-party marketing account. All payments must name this designated separate RERA escrow account.

Building Progress vs Money Spent

Are you paying for real progress on the ground?
Audited Bills

We check the engineer's on-site building reports against audited expense filings. This protects you from builders taking advance cash before actually pouring the slabs.

Physical Site Progress:77% Completed
Land Costβ‚Ή7.4 Cr31% of outlay
Building Costβ‚Ή16.1 Cr69% of outlay
Total Outlayβ‚Ή23.5 CrForm 3 CA Total
Financial Divergence Risk:Low / In-Sync

Expenditure certifications on Form 3 are proportional to physical superstructure milestones recorded by the site engineer.

Source: Chartered Accountant Form 3 & Engineer Form 2

Real Usable Flat Space vs Extra Charged Area

What you live inside vs stairs and lobby
Protected by Law

Before RERA, builders charged extra money by adding 30–40% phantom area for common stairs and lobbies. RERA mandates that you pay strictly for your actual room space inside inner walls.

Actual Usable Room SpaceInternal usable space between inner walls (what you physically live in)
100% Legal Basis
Private Balcony AreaAttached private balcony, measured separately
Disclosed Separately
Extra Common Space (Loading)Ratio of common stairs & lifts added by marketing brochures
~26%–30% (Typical)
Declared Unit Sizes on Record
Standard Plot / Unit1000 Sq.Ft. (92.9 mΒ²)
Large Plot / Unit1300 Sq.Ft. (120.8 mΒ²)
Agreement Clause Check: Make sure your sale agreement explicitly writes down the exact room carpet area. If the finished flat is more than 3% smaller than promised, the builder must refund the difference with interest.

6 Essential Checks Before You Pay

Checked Against Official State Records
On record

Every smart homebuyer checks these 6 points before paying more than the 10% token booking advance.

1. 30-Year Land Ownership Check
Freehold Title Verified by Sub-Registrar Jabalpur
Verified
2. Bank Loans on the Land
No hidden private loans or mortgages on record
Verified
3. Approved Building Blueprint
Sanctioned by Town Planning & Municipal Authority
Verified
4. Permission to Build (Commencement)
Authorizes physical ground construction & towers
Verified
5. Fire Safety & Environmental Clearances
High-rise fire life safety clearance approved
Verified
6. Bank Statements & Progress Reports
Quarterly construction and bank audit filings on Madhya Pradesh RERA
Verified
Cross-checked against state registry filings
Essential Homebuyer Due Diligence

Legal Guides for SWASTIK VILLAS PHASE-I

View all 12 due diligence guides