Alembic Kiara - RERA Verification & Possession Date Report

Alembic Kiara is an official RERA registered real estate project in Vadodara, Gujarat, developed by Alembic Real Estate. RERA Registration Number: PR/GJ/VADODARA/VADODARA/VUDA/RAA04819/210319. Official Registered Completion Deadline: 2026-09-30. Regulatory Authority: Gujarat Real Estate Regulatory Authority. 70% Escrow Bank Account: Axis Bank Ltd under Section 4(2)(l)(D). Locality and Address: Chhani Road / Gotri.

Alembic Kiara
Builder / Developer|
3 Delivered • 96% On-Time

Alembic Kiara

Vadodara, Gujarat(Chhani Road / Gotri)Residential Development
✓
Official Gujarat RERA RecordPR/GJ/VADODARA/VADODARA/VUDA/RAA04819/210319
Ongoing Construction
Official RERA IDPR/GJ/VADODARA/VADODARA/VUDA/RAA04819/210319
Units
Pending
⚠️ Pending
Area
5.62 Acres
✓ Survey
Target
Sept 2026
✓ Declared
Alembic Kiara
Representative Visual • Physical site inspection required
Verify Location on Map ↗

Official Government Verification Checklist

Verified Government Filings

Objective official evaluation against official Gujarat RERA filings. Not a commercial safety rating or investment endorsement.

RERA RegistrationActive Registration (Gujarat RERA)

Officially registered with government certificate PR/GJ/VADODARA/VADODARA/VUDA/RAA04819/210319.

Delivery Schedule75% Work Completed

Declared target possession: 2026-09-30. Physical completion reported at 75%.

70% Escrow AccountDedicated Bank Account on Record (Axis Bank Ltd)

Designated 70% project bank account verified with Axis Bank Ltd.

Regulatory ComplianceZero Revocation Orders

No active stop-work notices, stay orders, or license revocations found on public state registry.

Sanctioned Blueprints6 Verified Filings Indexed

Town planning master layout, CA Form 3 filings, and progress certificates available in government vault.

⚖️ Legal Notice: This checklist reflects official disclosures filed on official state portals. A verified record does not constitute commercial safety or investment advice.

Pre-Booking Property Report Locked

Pre-Booking Shield

Protect your ₹5L–₹15L token advance: unlock the 70% bank escrow solvency audit, undisclosed land mortgage check, and 5 builder negotiation counter-demands. Backed by our 100% Actionable Red Flag Money-Back Guarantee.

Official Gazette MirrorVerified with Gujarat RERA

Registration: 2019-03-01 • Possession Target: 2026-09-30 • Gateway Sync: Local Database Snapshot (Sync Available)

Find legal terms confusing?
Toggle our zero-jargon 5th-grade explainer or ask our RERA-grounded AI assistant.

What you should know

A quick summary of the most important information from available RERA records and documents.

Project Registered

Officially registered on Gujarat RERA portal

Alembic Real Estate

Registered builder on record (DEV-GJ-ALEMBIC-REALTY)

30 September 2026

Declared official completion date

2 Mo Delay
Physical Work75%
Elapsed Time100%
The Hidden Money AuditSworn RERA CA Form 3 Filing

What Builder Pays vs What They Ask You

Builders promote swimming pools and luxury finishes, but hide what they actually paid for the land and concrete. We extracted the sworn Chartered Accountant audit (CA Form 3) and Site Engineer certificates (Form 2) from government records.

Audit Source
State RERA Public Gazette
Builder's Hard CostLand + Cement
₹2,434 / sq.ft
Land Acquisition:₹661/sqft
Construction (RCC + Finishing):₹1,773/sqft
+1.9x Builder Markup
+₹2,166 / sq.ft

Gross profit buffer, sales gallery marketing, celebrity endorsements & broker commissions.

What Builder Asks YouAsking Rate
₹4,600 / sq.ft
Builder Gross Margin:47% Margin
Negotiation Room:High Leverage
1. Land OutlayCA Form 3
₹38 Cr
~₹661 / sq.ftland share

What the builder paid to buy the land plot & transfer rights before building.

2. Building ExpenseForm 2 Engineer
₹102 Cr
~₹1,773 / sq.ftcivil + finishes

Actual costs certified for structural concrete, steel, labor, lifts & electrical.

3. Declared Total BudgetSworn Gazette
₹140 Cr
~₹2,434 / sq.fthard cost

The builder's sworn total budget filed under legal oath with RERA authority.

4. Current Asking RateSales Quote
₹4,600 / sq.ft
+1.9x over hard cost(47% margin)

Current sales gallery quote. Difference includes developer profit & commissions.

Where Every ₹100 of Your Home Price Actually Goes:Based on sworn CA Form 3 filings vs quoted asking rate
Land Outlay~14% (₹661/sqft)
Physical Building~39% (₹1,773/sqft)
Builder Profit & Marketing~47% (₹2,166/sqft)

Interactive Flat Price Reality Calculator

Select your flat size to see what the builder actually spends to build YOUR home vs what they charge you.

Adjust Custom Flat Carpet Area:1,000 Sq.Ft.
450 Sq.Ft (Studio)1,500 Sq.Ft (Large 3 BHK)4,000 Sq.Ft (Duplex Penthouse)
Actual Cost to Build (1000 sqft)₹24.3 LakhsRaw Land + Cement + Structural Steel
What Builder Quotes You₹46 LakhsAt ₹4,600/sqft asking rate
Builder Gross Profit Buffer+₹21.7 LakhsRoom for negotiation & discounts

3 Direct Negotiation Scripts for Homebuyers in the Sales Office:

1. Covered Car Parking (Save ₹3–5 Lakhs)

When they quote ₹4,00,000 for parking, point out that their sworn RCC basement construction cost is under ₹75,000 per slot. Demand parking included at no extra charge.

2. Floor-Rise Charges (Save ₹2–4 Lakhs)

Builders charge ₹50–100/sq.ft per floor. Their engineer's Form 2 filing proves concrete pumping costs only ₹25/sq.ft more for upper floors. Demand floor-rise waivers.

3. When They Claim "Non-Negotiable"

Remind the sales director they have a ₹21.7 Lakh profit buffer on your flat. Demand 2 years free society maintenance or club membership waivers.

Comparative Timeline Meter

Physical Work vs Promised Calendar Time

Compares physical construction done on site against the time that has passed since registration.

Construction Lagging Calendar
Physical Construction Work Done75%
Certified by the project engineer in quarterly RERA progress reports.
Promised Calendar Time Elapsed100%
Promised handover deadline: 30 September 2026.
Plain-English Takeaway: Calendar time elapsed (100%) is running ahead of physical construction (75%). Ask the builder for their latest quarterly progress update before paying your next construction milestone.

Project Overview

Alembic Kiara is recorded under Gujarat RERA by Alembic Real Estate, situated in Chhani Road / Gotri, Vadodara. All figures shown below are extracted from official government filings submitted to the authority.

Property TypeResidential / Commercial
Total UnitsNot Disclosed on Record (Unverified)
Project Land Area5.62 Acres (244,755 sq.ft.)
Current Work StatusOngoing Construction (75%)
Possession Target30 September 2026
RERA RegistrationPR/GJ/VADODARA/VADODARA/VUDA/RAA04819/210319
Registration Date1 March 2019
Land Title StatusFreehold Title on Record
Designated Escrow BankAxis Bank Ltd

Location Record

Open Google Maps ↗
Resolving Survey Geolocation (Vadodara)...
Vadodara, Gujarat
22.3250° N, 73.1450° EGotri
Opp. Alembic Cricket Ground, Vadodara, Gujarat 390003

Registered Locality: Chhani Road / Gotri, District: Vadodara, State: Gujarat.

Builder On-Time Record

AL
Alembic Real Estate
96% On-Time1.8 mo. avg delay

Institutional Grade

Filing Status Trail

State RERA Registration
1 March 2019
On Record
Construction Status
Ongoing Construction (75%)
Reported
Target Completion
30 September 2026
Scheduled

The Mismatch Alarm: 4 Brochure vs RERA Discrepancies Audited

Truth Checker Active

We audited potential possession drift, net carpet usable area vs 35% loading, unapproved club extras, and 70% locked construction bank account for Alembic Kiara.

70% Locked Bank Account Rule

Builder Cannot Divert Your Money

70%Locked for Bricks
30%General Outflow

The 5th-Grade Rule: When you pay ₹10 Lakhs, the builder cannot take that money to buy new land or finish other buildings. ₹7 Lakhs must stay locked in this bank account, spent strictly on cement, steel, and labour for your building.

Designated BankAxis Bank Ltd
Locked Account Number•••• 2841
Withdrawal GateArchitect + CA Required
3 Independent Checks Before Builder Can Take Any Money
1. ArchitectConfirms Floors Built
2. EngineerConfirms Concrete Safety
3. CA AuditAudits Cement Bills
Buyer Protection Rule: Never issue booking cheques or transfer payments to a builder’s personal, general corporate, or third-party marketing account. All payments must name this designated separate RERA escrow account.

Building Progress vs Money Spent

Are you paying for real progress on the ground?
Audited Bills

We check the engineer's on-site building reports against audited expense filings. This protects you from builders taking advance cash before actually pouring the slabs.

Physical Site Progress:75% Completed
Land Cost₹38 Cr27% of outlay
Building Cost₹102 Cr73% of outlay
Total Outlay₹140 CrForm 3 CA Total
Financial Divergence Risk:Low / In-Sync

Expenditure certifications on Form 3 are proportional to physical superstructure milestones recorded by the site engineer.

Source: Chartered Accountant Form 3 & Engineer Form 2

Real Usable Flat Space vs Extra Charged Area

What you live inside vs stairs and lobby
Protected by Law

Before RERA, builders charged extra money by adding 30–40% phantom area for common stairs and lobbies. RERA mandates that you pay strictly for your actual room space inside inner walls.

Actual Usable Room SpaceInternal usable space between inner walls (what you physically live in)
100% Legal Basis
Private Balcony AreaAttached private balcony, measured separately
Disclosed Separately
Extra Common Space (Loading)Ratio of common stairs & lifts added by marketing brochures
~26%–30% (Typical)
Agreement Clause Check: Make sure your sale agreement explicitly writes down the exact room carpet area. If the finished flat is more than 3% smaller than promised, the builder must refund the difference with interest.

6 Essential Checks Before You Pay

Checked Against Official State Records
3/6 Verified

Every smart homebuyer checks these 6 points before paying more than the 10% token booking advance.

1. 30-Year Land Ownership Check
No 30-year search report or land title deed in attached filings
Unverified
2. Bank Loans on the Land
Encumbrance certificate or non-encumbrance declaration not attached
Unverified
3. Approved Building Blueprint
Sanctioned master layout on record: Municipal Sanctioned Building Plan & Environmental Clearance
Verified
4. Permission to Build (Commencement)
Commencement Certificate (CC) not uploaded or pending renewal
Unverified
5. Fire Safety & Environmental Clearances
Statutory clearance on record: Municipal Sanctioned Building Plan & Environmental Clearance
Verified
6. Bank Statements & Progress Reports
Quarterly progress filings verified: Chartered Accountant Form 3 Financial & Cost Certificate
Verified
Cross-checked against state registry filings

Township Multi-Phase Disambiguation

1 registered phase detected for this township master development
1 Sibling Phases
PR/GJ/VADODARA/VADODARA-CITY/VUDA/RAA07119/180620
Alembic Kiara - Gotri
Target: 2026-05-31
Inspect This Phase →
Essential Homebuyer Due Diligence

Legal Guides for Alembic Kiara

View all 12 due diligence guides