RERA: P51800012353RERA Approved Ready to Move (100% Complete)

Gera Malad County

Promoter / Developer:Gera Mumbai Homes Pvt. Ltd.•Malad West, Mumbai Suburban, Maharashtra

Data directly synced with MahaRERA (Government of Maharashtra)
Certified Land Cost

₹32 Cr

Form 3 CA Certificate
Construction Budget

₹64.01 Cr

Form 2 Site Engineer
Official Possession Date

30-11-2024

Delayed by 672 days
70% RERA Escrow Bank

ICICI Bank Ltd.

A/C: ••••0542

Certified Cost Audit (Form 3 Filing)

CA Certified (Form 3)

Under Section 4(2)(l)(D) of the Real Estate (Regulation and Development) Act 2016, 70% of all amounts realized for the real estate project from the allottees must be deposited in a separate bank account to cover the cost of construction and the land cost.

Certified Land Cost

₹32 Cr

Construction Spend

₹64.01 Cr

Total Project Outlay

₹96.01 Cr

Mandatory Statutory Buyer Escrow Protection (RERA Act 2016 § 4(2)(l)(D)):

Before transferring any booking token or executing RTGS/cheque transfers, buyers MUST cross-verify the project bank account details against the promoter's physical stamped Form C Registration Certificate. Never transfer funds to any personal, marketing broker, or unverified current account.

Bank: ICICI Bank Ltd.•A/C: ••••0542 (Escrow)•IFSC: ICIC0000391

Official Government Filings (6 Documents on Record)

Source: MahaRERA (Government of Maharashtra)

Official RERA Registration Certificate

Statutory registration certificate granted by MahaRERA (Government of Maharashtra) confirming legal sanction under Registration No. P51800012353.

Official Government Vault Record

Municipal Sanctioned Building Plan & Layout Sanction

Town and Country Planning approved structural layouts, sanctioned floor heights, and site setback clearances.

Official Government Vault Record

Chartered Accountant Form 3 Financial Audit & Cost Ledger

Statutory quarterly ledger verifying ₹32 Cr land outlay and ₹96.01 Cr project cost.

Official Government Vault Record

70% Designated Escrow Bank Account Maintenance Declaration

Designated separate escrow account with ICICI Bank Ltd. safeguarding buyer funds under RERA Section 4(2)(l)(D).

Official Government Vault Record

Engineer Progress Quarterly Verification Report (Form 2)

Independent chartered engineer audit confirming 100% physical civil construction completion.

Official Government Vault Record

Agreement for Sale (Statutory State RERA Standard Form Draft)

Statutory draft contract guaranteeing delivery dates, carpet area verification, and five-year defect liability.

Official Government Vault Record
Property Verification Audit1 Credit Access

Unlock Full Due-Diligence Report

Protect your advance token with our comprehensive property safety audit.

Contradiction Radar: Form 5 delay & extension detector
Sales Agreement vs RERA Model Contract diff
5 dynamic interrogation questions for builder
Instant watermarked PDF report download
1 Creditor from ₹499Free for New Accounts

Instant unlock • 1-Year access • 100% money-back accuracy guarantee

Land Title & Ownership

Builder Owns Land 100% (Freehold)

Sale Deed Reg. #MH-MUM-2022-8406

Promoter Track RecordTier-1 Institutional Track Record

Gera Mumbai Homes Pvt. Ltd.

Tracked Projects7 Registered
On-Time Score100%

Plot / Survey No. 27, Malad West, Mumbai Suburban, Maharashtra

View complete builder portfolio in directory
Important Information for Property Buyers

This page brings together the official public papers, progress updates, approved building maps, and notifications submitted by the builder to the government real estate authority (MahaRERA (Government of Maharashtra)).

OwnProperty shows these government records exactly as filed by the builder. The dates, work progress, and bank details shown here come directly from what the builder reported. Before paying any token money or signing a sale agreement, we strongly advise you to check the original stamped paper certificate and have an experienced lawyer review the property documents.