RERA Market Intelligence Hub
Sagar Property Market Due Diligence
Official RERA completion records for 104 developments registered across Sagar. Cross-reference completion timelines, 70% escrow accounts, and builder delivery track records before paying a booking deposit.
Micro-Market Delay Rate
53.8%
56 of 104 overdueTotal RERA Projects104
Ready to Move32
Under Construction71
Total Investment₹914 Cr
High Delay Alert for Sagar: 53.8% Overdue Rate
Always verify the sworn Form C possession date and inspect CA Form 3 withdrawal filings before signing an agreement in Sagar. If a project has exceeded its completion date without an official RERA extension, you are entitled to monthly delay compensation under Section 18.
Builder Track Records
View all buildersBuilders Active in Sagar
Registered Developer Firm20% On-Time
KALPDHAM BUILDERS AND DEVELOPERS
16 Registered ProjectsReport
Registered Developer Firm50% On-Time
KALPDHAM SAGAR DEVELOPERS
5 Registered ProjectsReport
Public/Private Limited Company50% On-Time
KHANNA PROPERTIES & INFRASTRUCTURES PVT LTD
5 Registered ProjectsReport
Public/Private Limited Company0% On-Time
OM ACCESS REALTY PVT.LTD.
5 Registered ProjectsReport
Registered Developer Firm75% On-Time
PREMENDRA RICHHARIYA
4 Registered ProjectsReport
Registered Developer Firm33% On-Time
RAJ BUILDERS
4 Registered ProjectsReport
Registered Developer Firm100% On-Time
RICHHARIYA BUILDERS AND DEVELOPERS
3 Registered ProjectsReport
Public/Private Limited Company67% On-Time
GEETANJALI BUILDERS PRIVATE LIMITED
3 Registered ProjectsReport
Registered Developer Firm67% On-Time
PRAKASH CHOUBEY
3 Registered ProjectsReport
Registered Developer Firm50% On-Time
POORAN LAL AHIRWAR
3 Registered ProjectsReport
Public/Private Limited Company0% On-Time
KALPDHAM INFRATECH PVT. LTD.
3 Registered ProjectsReport
Registered Developer Firm100% On-Time
YADU BUILDERS AND DEVELOPERS
2 Registered ProjectsReport
Official Directory
Filter Sagar projectsRegistered Developments in Sagar (104)
MP-GOV-SAG-ZkM1TzY0VkWork Going On
CONST OF 37 HIG-A 17 LIG-A 26 LIG-B 142 EWS-B & DEV OF LAND DR H S GOUR NAGAR SAG
By EXECUTIVE ENGINEER M P HOUSING AND INF DEV BOARD DIV SAGAR
Possession Date:2026-12-31
Verify Property Report
MP-GOV-SAG-UkVYcUhtSXWork Going On
CONSTRUCTION OF 30 HIG B 34 MIG A 30 MIG B 56 LIG A 25 LIG B AT PT. D.D.NAGAR SAGAR
By M.P.HOUSING BOARD DIVISION SAGAR
Possession Date:2021-04-30
Verify Property Report
MP-GOV-SAG-Mm5JNTh2bWWork Going On
CONST OF 7 HIG( A) 24 HIG (B) 10 MIG (A) 17 LIG (A) 19 LIG( B) 76 EWS (A) 27 EWS (B) AT DR H S GOUR
By M.P.HOUSING & INF DEV BOARD DIVISION SAGAR
Possession Date:2019-04-30
Verify Property Report
MP-GOV-SAG-bFBUWW5JdGWork Going On
CONST OF 25 HIG(A) 9 LIG(A) 11LIG(B) 78 EWS(B) AND LAND DEVELOPMENT WORK AT DR HARI SINGH GOUR NAGAR
By M.P.HOUSING & INF DEV BOARD DIVISION SAGAR
Possession Date:2027-12-31
Verify Property Report
MP-GOV-SAG-Wk9rSVpQVUWork Going On
CONSTRUCTION OF 155 LIG 70 EWS HOUSES AND DEV. 5 HECT LAND AT AADARSH NAGR JAGDISHPURA KHURAI SAGAR
By K.L.AHIRWAR EXECUTIVE ENGINEER M.P.HOUSING & INF.DEV.BOARD DIVISION SAGAR
Possession Date:2025-08-16
Verify Property Report
MP-GOV-SAG-dXpVUWtaUWReady to Move
SUNRISE MEGA CITY PHASE - 4
By PRAKASH CHOUBEY
Possession Date:2026-08-23
Verify Property Report
MP-GOV-SAG-VkxaSDR5OXWork Going On
DEEN DAYAL COMMERCIAL COMPLEX,KATRA BAZAAR,SAGAR
By POORAN LAL AHIRWAR
Possession Date:2023-04-15
Verify Property Report
MP-GOV-SAG-RE96OFYwbWWork Going On
UDAY RESIDENCY
By KALPDHAM BUILDERS AND DEVELOPERS
Possession Date:2027-12-31
Verify Property Report
MP-GOV-SAG-UUs3Q3pGbmReady to Move
CONST OF 36 LIG (A) 25 LIG(B) 46 EWS (A) 31 EWS(B) AT DR H S GOUR NAGAR SAGAR
By SYED NASIR ALI E E M P HOUSING AND INF DEV BOARD SAGAR
Possession Date:2020-12-31
Verify Property Report
MP-GOV-SAG-V1dja2xrWlWork Going On
KALPDHAM GALAXY
By SHIV SAGAR ASSOCIATE
Possession Date:2025-12-31
Verify Property Report
MP-GOV-SAG-MnNOUUFzc1Ready to Move
GEETANJALI GREENS CITY PHASE -2
By GEETANJALI BUILDERS PRIVATE LIMITED
Possession Date:2021-06-01
Verify Property Report
MP-GOV-SAG-WmpyK0FuR0Work Going On
SAGARSHREE ENCLAVE
By SHRI PARASNATH ASSOCIATES
Possession Date:2026-12-31
Verify Property Report
MP-GOV-SAG-MzFHQUpSeUWork Going On
CONSTRUCTION OF 31 HIG (B) 27 MIG (A) AT DR.HARI SINGH GOUR NAGAR SAGAR M.P. PHASE (3)
By M.C.GHANGHORIA EXECUTIVE ENGINEER M.P.HOUSING AND INF.DEV BOARD DIV.SAGAR
Possession Date:2022-03-31
Verify Property Report
MP-GOV-SAG-VWZSK3dva1Work Going On
PRAKASH RESIDENCY
By SUMIT SINGH TOMAR
Possession Date:2024-12-31
Verify Property Report
MP-GOV-SAG-UkVKQ21lcHReady to Move
SAMDARIYA HIGH STREET MALL
By SAMDARIYA BUILDERS RAHATGARH PVT LTD
Possession Date:2024-12-31
Verify Property Report
MP-GOV-SAG-QytNZE9uSEWork Going On
PALM VALLEY
By SUNIL JADIYA
Possession Date:2026-12-31
Verify Property Report
MP-GOV-SAG-clJXS2U0aUWork Going On
GANGA ELITE
By INDRAJEET YADAV
Possession Date:2024-12-31
Verify Property Report
MP-GOV-SAG-VGN3SjNRRlReady to Move
MANSAROVAR COLONY
By NAW NIRMAN BUILDERS
Possession Date:2018-12-31
Verify Property Report
MP-GOV-SAG-b3N0S3doaGReady to Move
ASHOK VIHAR COLONY
By RAJ BUILDERS
Possession Date:2023-01-31
Verify Property Report
MP-GOV-SAG-cG9obW1uL2Ready to Move
MAHAMAYA RESIDENCY
By RICHHARIYA BUILDERS AND DEVELOPERS
Possession Date:2024-12-31
Verify Property Report
MP-GOV-SAG-dTRGRkdwWEWork Going On
DHARAM SHREE COLONY
By M.P.HOUSING BOARD DIVISION SAGAR
Possession Date:2025-12-31
Verify Property Report
MP-GOV-SAG-Y2hGekwyTkWork Going On
KRISHNA VALLEY
By KALPDHAM SAGAR DEVELOPERS
Possession Date:2026-12-31
Verify Property Report
MP-GOV-SAG-THFUczNOR0Ready to Move
GOPALA RESIDENCY
By GOPALA BUILDERS INFRASTRUCTURE
Possession Date:2027-12-31
Verify Property Report
MP-GOV-SAG-UXBKeE1QTnWork Going On
MOHAN ENCLAVE PHASE-II
By KALPDHAM BUILDERS AND DEVELOPERS
Possession Date:2025-12-31
Verify Property Report