Back to Builders DirectoryEntity ID:
DEV-13658Builder Risk IntelligenceRegistered Developer FirmSingle Project — Past Completion Deadline
MADHYA PRADESH HOUSING AND INFRASTRUCTURE DEVELOPMENT BOARD, DIVISION 3, BHOPAL
206/bagmugalia/42/4
Track Record Rating
0 of 1 delivered on record
Sample size under 10 projects. Raw counts displayed per reporting standard.Total Projects1
Completed0
Ongoing1
Delayed1
Avg Delay90m
Portfolio Value₹12.45 Cr
Official RERA Evaluation
Escrow & Delivery Analysis
Under Section 4(2)(l)(D) of RERA, 70% of collections from buyers for every project registered by MADHYA PRADESH HOUSING AND INFRASTRUCTURE DEVELOPMENT BOARD, DIVISION 3, BHOPAL must be held in a designated scheduled bank escrow account. Before booking in any project by this developer, verify the CA Form 3 withdrawal certificate and confirm whether site progress matches architect declarations.
Certified under State RERA Authorities
Direct government record verification
Project Portfolio
Official filings on record