Back to Builders DirectoryEntity ID:
DEV-10210Builder Risk IntelligenceRegistered Developer FirmChronic Delay Risk
SATISH GAUR
PH NO. 4& 17, KH NO. 2/1, 2/2, 3/1 & P/O 27 VILLAGE LAXMIPUR & LAMTI JABALPUR
Track Record Rating
1 of 7 delivered on record
Sample size under 10 projects. Raw counts displayed per reporting standard.Total Projects7
Completed1
Ongoing6
Delayed6
Avg Delay44.5m
Portfolio Value₹54.17 Cr
Official RERA Evaluation
Escrow & Delivery Analysis
Under Section 4(2)(l)(D) of RERA, 70% of collections from buyers for every project registered by SATISH GAUR must be held in a designated scheduled bank escrow account. Before booking in any project by this developer, verify the CA Form 3 withdrawal certificate and confirm whether site progress matches architect declarations.
Certified under State RERA Authorities
Direct government record verification
Project Portfolio
Official filings on recordRegistered RERA Projects (7)
P-JBP-21-3047Work Going On
SAKAR TAPOBHOOMI PHASE-II
Jabalpur (Jabalpur), Jabalpur, Madhya Pradesh
Completion Date:2024-02-10
Check Property Report
P-JBP-17-4408Ready to Move
SAKAR TAPOBHOOMI
Jabalpur (Jabalpur), Jabalpur, Madhya Pradesh
Completion Date:2018-11-23
Check Property Report
MP-GOV-SEO-THIvdzQ3RzWork Going On
SAKAR HEIGHTS
Seoni (Seoni), Seoni, Madhya Pradesh
Completion Date:2020-01-11
Check Property Report
P-JBP-22-3259
Active Under Construction
SAKAR CITY PHASE III
Jabalpur, Jabalpur, Madhya Pradesh
Completion Date:2024-01-14
Check Property Report
MP-GOV-SEO-WDdwKzFxL1Work Going On
SAKAR CITY PHASE II
Seoni (Seoni), Seoni, Madhya Pradesh
Completion Date:2022-10-24
Check Property Report
P-JBP-23-4279Work Going On
SAKAR TAPOVAN
Jabalpur (Jabalpur), Jabalpur, Madhya Pradesh
Completion Date:2026-04-30
Check Property Report
MP-GOV-NAR-ZlhvWlY5SWWork Going On
SAKAR SHREE BHAGWANT CITY
Other (Narsinghpur), Narsinghpur, Madhya Pradesh
Completion Date:2021-01-11
Check Property Report