SHUBHAM REALTY
12/3,12/4, 9 (PART) Chhota Bangarda, Super Corridor,
Indore MP
Track Record Rating
38%
On-Time Handover RateTotal Projects8
Completed3
Ongoing5
Delayed5
Avg Delay44m
Portfolio Value₹130.08 Cr
Official RERA Evaluation
Escrow & Delivery Analysis
Under Section 4(2)(l)(D) of RERA, 70% of collections from buyers for every project registered by SHUBHAM REALTY must be held in a designated scheduled bank escrow account. Before booking in any project by this developer, verify the CA Form 3 withdrawal certificate and confirm whether site progress matches architect declarations.
Certified under State RERA Authorities
Direct government record verification
Project Portfolio
Official filings on recordRegistered RERA Projects (10)
MP-GOV-IND-dXlnTEVjVUReady to Move
SHUBHAM NARIMAN ENCLAVE
Indore (Indore), Indore, Madhya Pradesh
Completion Date:31-07-2018
Check Property Report
P-JBP-17-336Registration Withdrawn
ASTHA NAGAR
Jabalpur (Jabalpur), Jabalpur, Madhya Pradesh
Completion Date:31-12-2027
Check Property Report
MP-GOV-IND-VnZnVURzekReady to Move
SHUBHAM NARIMAN ENCLAVE BUILDING NO 1
Indore (Indore), Indore, Madhya Pradesh
Completion Date:30-04-2020
Check Property Report
MP-GOV-IND-YnJMY0xHV0Work Going On
SHUBHAM NARIMAN ENCLAVE BUILDING NO.2
Indore (Indore), Indore, Madhya Pradesh
Completion Date:01-01-2022
Check Property Report
MP-GOV-IND-R2Q0NUVEOHReady to Move
LAABHAM PARK
Indore (Indore), Indore, Madhya Pradesh
Completion Date:20-02-2022
Check Property Report
MP-GOV-IND-MkVtM0FaV3Work Going On
LAABHAM PARK-2
Indore (Indore), Indore, Madhya Pradesh
Completion Date:01-01-2023
Check Property Report
P-OTH-23-4052
Active Under Construction
LAABHAM HILLS
Juni Indore, Indore, Madhya Pradesh
Completion Date:15-05-2026
Check Property Report
MP-GOV-JAB-d3VSVnM5dURegistration Withdrawn
ASTHA NAGAR
Jabalpur (Jabalpur), Jabalpur, Madhya Pradesh
Completion Date:31-12-2025
Check Property Report
MP-GOV-IND-dHBuR0JaYXWork Going On
SVN LAABHAM CITY
Indore (Indore), Indore, Madhya Pradesh
Completion Date:15-08-2022
Check Property Report
MP-GOV-IND-N1YrUG9QU0Work Going On
SHUBHAM NARIMAN ENCLAVE BUILDING NO. 4
Other (Indore), Indore, Madhya Pradesh
Completion Date:01-07-2021
Check Property Report