Back to Builders DirectoryEntity ID:
DEV-10107Builder Risk IntelligenceRegistered Developer FirmRegulatory Sanction / Revocation on Record
EXECUTIVE ENGINEER M P HOUSING AND INFRASTRUCTURE DEVELOPMENT BOARD DN-2 GWALIOR
Sector B Deen Dayal Nagar Gwalior
Track Record Rating
2 of 8 delivered on record
Sample size under 10 projects. Raw counts displayed per reporting standard.Total Projects9
Completed2
Ongoing6
Delayed6
Avg Delay37.8m
Portfolio Value₹425.94 Cr
Official RERA Evaluation
Escrow & Delivery Analysis
Under Section 4(2)(l)(D) of RERA, 70% of collections from buyers for every project registered by EXECUTIVE ENGINEER M P HOUSING AND INFRASTRUCTURE DEVELOPMENT BOARD DN-2 GWALIOR must be held in a designated scheduled bank escrow account. Before booking in any project by this developer, verify the CA Form 3 withdrawal certificate and confirm whether site progress matches architect declarations.
Certified under State RERA Authorities
Direct government record verification
Project Portfolio
Official filings on recordRegistered RERA Projects (9)
MP-GOV-GWA-djBTTm9uZGWork Going On
SURYA NAGAR PHASE 1ST (191 HOUSES WITH DEVELOPEMENT ) LAXMANGARH BARETHA ) GWALIOR
Gwalior (Gwalior), Gwalior, Madhya Pradesh
Completion Date:2025-10-31
Check Property Report
MP-GOV-GWA-STZRcEs0aWWork Going On
CONSTRUCTION OF 246 (150 LIG AND 96 EWS ) HOUSES INCLUDING DEVELOPMENT WORK AT " GIRNAAR PARIS
Gwalior (Gwalior), Gwalior, Madhya Pradesh
Completion Date:2025-11-30
Check Property Report
MP-GOV-GWA-WjNSdmMwWWWork Going On
CONSTRUCTION OF 126 (90 LIG + 36 EWS ) HOUSES ATAL AASHRAY YOJNA GIRNAAR PARISAR PHASE 1 , GIRGAO
Gwalior (Gwalior), Gwalior, Madhya Pradesh
Completion Date:2020-12-31
Check Property Report
MP-GOV-GWA-TWZJaEtEWmReady to Move
MIXED PROJECT FOR 104 DIFFERENT TYPE HOUSE ( 56 HOUSES + 48 PLOTS) AT &#039
Gwalior (Gwalior), Gwalior, Madhya Pradesh
Completion Date:2019-08-12
Check Property Report
MP-GOV-GWA-cVNVMkxlalReady to Move
SHOP CUM RESIDENCE ( 36 SHOPS) AT 'SECTOR F' POCKET "B" D D NAGAR GWALIOR MP
Gwalior (Gwalior), Gwalior, Madhya Pradesh
Completion Date:2020-06-30
Check Property Report
MP-GOV-GWA-blNNQmd6Q2Work Going On
COMMERCIAL CUM RESIDENTIAL COMPLEX ( 22 SHOPS + 8 FLATS ) POCKET 'A' SECTOR 'F'
Gwalior (Gwalior), Gwalior, Madhya Pradesh
Completion Date:2018-12-13
Check Property Report
MP-GOV-GWA-aUZwejhRWEWork Going On
NEW TOWNSHIP THATIPUR GWALIOR (COMMERCIAL CORRIDOR)
Gwalior (Gwalior), Gwalior, Madhya Pradesh
Completion Date:2024-09-20
Check Property Report
MP-GOV-GWA-N3dCa2d2VDReady to Move
COMMERCIAL CUM RESIDENTIAL COMPLEX, NEW TOWNSHIP THATIPUR GWALIOR CLP-1 UNDER REDENSIFICATION SCHEME
Gwalior (Gwalior), Gwalior, Madhya Pradesh
Completion Date:2027-12-31
Check Property Report
MP-GOV-GWA-anRuRmEyQVWork Going On
RESIDENTIAL CUM COMMERCIAL COMPLEX SECTOR A DEEN DAYAL NAGAR GWALIOR
Gwalior (Gwalior), Gwalior, Madhya Pradesh
Completion Date:2025-03-07
Check Property Report
