Track Record Rating
11%
On-Time Handover RateTotal Projects12
Completed1
Ongoing9
Delayed8
Avg Delay60.9m
Portfolio Value₹391.01 Cr
Official RERA Evaluation
Escrow & Delivery Analysis
Under Section 4(2)(l)(D) of RERA, 70% of collections from buyers for every project registered by SAMDARIYA BUILDERS PVT LTD must be held in a designated scheduled bank escrow account. Before booking in any project by this developer, verify the CA Form 3 withdrawal certificate and confirm whether site progress matches architect declarations.
Certified under State RERA Authorities
Direct government record verification
Project Portfolio
Official filings on recordRegistered RERA Projects (15)
P-RWA-17-801Work Going On
SAMDARIYA GOLD
Rewa Area, Rewa, Madhya Pradesh
Completion Date:31-12-2021
Check Property Report
MP-GOV-REW-YlB2SW9oaDWork Going On
MEDICAL MALL
Rewa (Rewa), Rewa, Madhya Pradesh
Completion Date:13-10-2021
Check Property Report
MP-GOV-REW-eTB3Mjg1YlWork Going On
SHREE BALAJI GOLD
Rewa (Rewa), Rewa, Madhya Pradesh
Completion Date:18-10-2023
Check Property Report
MP-GOV-REW-M3J1UDZWS2Work Going On
SAMDARIYA ADARSH
Rewa (Rewa), Rewa, Madhya Pradesh
Completion Date:18-10-2022
Check Property Report
MP-GOV-JAB-K3VFMDlwbEWork Going On
RADHE KRISHNA VIHAR PHASE II
Jabalpur (Jabalpur), Jabalpur, Madhya Pradesh
Completion Date:31-12-2026
Check Property Report
P-JBP-17-802Work Going On
SAMDARIYA GOLD JABALPUR
Jabalpur (Jabalpur), Jabalpur, Madhya Pradesh
Completion Date:19-06-2019
Check Property Report
MP-GOV-JAB-dmp0L1VXRjRegistration Withdrawn
SAMDARIYA RESIDENCY
Jabalpur (Jabalpur), Jabalpur, Madhya Pradesh
Completion Date:28-02-2018
Check Property Report
P-JBP-17-803Work Going On
SAMDARIYA ROYAL HOMES
Jabalpur (Jabalpur), Jabalpur, Madhya Pradesh
Completion Date:12-04-2018
Check Property Report
MP-GOV-REW-bk93VlBXcFReady to Move
SAMDARIYA ANANT VAIBHAV
Rewa (Rewa), Rewa, Madhya Pradesh
Completion Date:23-07-2020
Check Property Report
MP-GOV-REW-WVNkRW9YdTWork Going On
SAMDARIYA GOLD
Rewa (Rewa), Rewa, Madhya Pradesh
Completion Date:31-12-2027
Check Property Report
MP-GOV-REW-c2tFai90eTWork Going On
HARDEV VAIBHAV
Rewa (Rewa), Rewa, Madhya Pradesh
Completion Date:23-10-2022
Check Property Report
REJECTED-JBP-3237Work Going On
RADHE KRISHNA VIHAR PHASE II
Jabalpur (Jabalpur), Jabalpur, Madhya Pradesh
Completion Date:31-12-2024
Check Property Report
MP-GOV-JAB-TTRGL2QzcUWork Going On
RADHE KRISHNA VIHAR PHASE II
Jabalpur (Jabalpur), Jabalpur, Madhya Pradesh
Completion Date:31-12-2027
Check Property Report
MP-GOV-REW-Qk9TVlkxS0Ready to Move
AWASTHI PLAZA
Rewa (Rewa), Rewa, Madhya Pradesh
Completion Date:08-12-2022
Check Property Report
P-JBP-19-2413Work Going On
KUBER CITY
Jabalpur (Jabalpur), Jabalpur, Madhya Pradesh
Completion Date:20-05-2022
Check Property Report