Registered Developer FirmRegulatory Sanction / Revocation on Record

MAHESH PARYANI

suevry no. 60/2, 61/1 and 61/2 gram hakkanipura tehsil ujjain
Track Record Rating
38%
On-Time Handover Rate
Total Projects15
Completed3
Ongoing11
Delayed5
Avg Delay22.2m
Portfolio Value₹115.79 Cr
Official RERA Evaluation

Escrow & Delivery Analysis

Under Section 4(2)(l)(D) of RERA, 70% of collections from buyers for every project registered by MAHESH PARYANI must be held in a designated scheduled bank escrow account. Before booking in any project by this developer, verify the CA Form 3 withdrawal certificate and confirm whether site progress matches architect declarations.

Certified under State RERA Authorities
Direct government record verification
Project Portfolio

Registered RERA Projects (17)

Official filings on record
MP-GOV-UJJ-VjdpUFFmTlWork Going On

TIRUPATI CRYSTAL C BLOCK

Other (Ujjain), Ujjain, Madhya Pradesh
Completion Date:31-12-2024
Check Property Report
MP-GOV-UJJ-b25FbHdkcUWork Going On

TIRUPATI EMERALD PARK EXT.

Ujjain (Ujjain), Ujjain, Madhya Pradesh
Completion Date:31-12-2027
Check Property Report
MP-GOV-JAB-MTBVWU5NQlWork Going On

MAYFARE ONE

Jabalpur (Jabalpur), Jabalpur, Madhya Pradesh
Completion Date:31-12-2024
Check Property Report
MP-GOV-UJJ-S2Y1UUIxZmWork Going On

CRYSTAL PREMIUM

Ujjain (Ujjain), Ujjain, Madhya Pradesh
Completion Date:31-12-2026
Check Property Report
MP-GOV-UJJ-ajFxZDVKQUWork Going On

TIRUPATI PALM VALLEY PHASE-1

Ujjain (Ujjain), Ujjain, Madhya Pradesh
Completion Date:31-12-2024
Check Property Report
APP-PENDING-JBP-5031Ready to Move

MAYFARE ONE

Jabalpur (Jabalpur), Jabalpur, Madhya Pradesh
Completion Date:31-12-2025
Check Property Report
MP-GOV-UJJ-THlpYWdlU1Ready to Move

TIRUPATI PALM VALLEY PHASE-2

Ujjain (Ujjain), Ujjain, Madhya Pradesh
Completion Date:31-12-2027
Check Property Report
MP-GOV-UJJ-S0x2REVnNnWork Going On

TIRUPATI CRYSTAL B BLOCK

Other (Ujjain), Ujjain, Madhya Pradesh
Completion Date:31-12-2025
Check Property Report
MP-GOV-UJJ-VTh6d3YzU0Work Going On

TIRUPATI CRYSTAL C EXT.

Other (Ujjain), Ujjain, Madhya Pradesh
Completion Date:31-12-2027
Check Property Report
MP-GOV-UJJ-UU10SnNRaWReady to Move

TIRUPATI PLATINUM -B

Other (Ujjain), Ujjain, Madhya Pradesh
Completion Date:01-03-2021
Check Property Report
MP-GOV-UJJ-eXg2Vmk5bjWork Going On

TIRUPATI PLATINUM A BLOCK

Ujjain (Ujjain), Ujjain, Madhya Pradesh
Completion Date:01-11-2022
Check Property Report
MP-GOV-UJJ-VHVQTm9CbkReady to Move

TIRUPATI PRIDE-30

Other (Ujjain), Ujjain, Madhya Pradesh
Completion Date:15-03-2027
Check Property Report
MP-GOV-UJJ-STIvR2syeDWork Going On

KRISHNA VIHAR

Ujjain (Ujjain), Ujjain, Madhya Pradesh
Completion Date:31-12-2027
Check Property Report
MP-GOV-UJJ-aFVONFFialWork Going On

KRISHNA VIHAR

Other (Ujjain), Ujjain, Madhya Pradesh
Completion Date:24-08-2025
Check Property Report
MP-GOV-UJJ-RnFPZGhJb0Work Going On

TIRUPATI DESIRE

Ujjain (Ujjain), Ujjain, Madhya Pradesh
Completion Date:25-10-2026
Check Property Report
MP-GOV-UJJ-SXhnVUxKWmWork Going On

TIRUPATI VOILET PARK

Ujjain (Ujjain), Ujjain, Madhya Pradesh
Completion Date:15-03-2027
Check Property Report
MP-GOV-UJJ-L3hicVFqb3Work Going On

TIRUPATI HOMES

Other (Ujjain), Ujjain, Madhya Pradesh
Completion Date:01-10-2027
Check Property Report