DLF The Arbour - Sector 63
Builder / Developer|
13 Delivered • 100% On-Time Record

DLF The Arbour - Sector 63

Gurugram, Haryana(Sector 63, Golf Course Extension Road)4 BHK Ultra Luxury (3,950 Sq.Ft.)RERA RegisteredWork Going On
RERA Number
RC/REP/HARERA/GGM/671/403/2023/15
✓ Government Registered
Total Units
Not Disclosed on Record
⚠️ Pending Filing
Project Area
25.71 Acres (1,120,000 sq.ft.)
✓ Land Survey
Possession Date
30 June 2028
✓ Declared in Filing
DLF The Arbour - Sector 63
Representative Visual • Physical site inspection required
Verify Location on Map ↗

Official Government Verification Checklist

Verified Government Filings

Objective official evaluation against official Haryana RERA filings. Not a commercial safety rating or investment endorsement.

RERA RegistrationActive Registration (Haryana RERA)

Officially registered with government certificate RC/REP/HARERA/GGM/671/403/2023/15.

Delivery Schedule42% Work Completed

Declared target possession: 2028-06-30. Physical completion reported at 42%.

70% Escrow AccountDedicated Bank Account on Record (State Bank of India)

Designated 70% project bank account verified with State Bank of India.

Regulatory ComplianceZero Revocation Orders

No active stop-work notices, stay orders, or license revocations found on public state registry.

Sanctioned Blueprints6 Verified Filings Indexed

Town planning master layout, CA Form 3 filings, and progress certificates available in government vault.

⚖️ Legal Notice: This checklist reflects official disclosures filed on official state portals. A verified record does not constitute commercial safety or investment advice.

Comprehensive Verification Report Unlocked

Full Access Active

You have unlocked the complete property check for this project, including safe bank account filings, late delivery penalty calculations, and Contradiction Radar.

Permanently Unlocked
Local Database Verified (Direct Government Record Mirror)Verified with Haryana Government

Last auto-synced: 2 hours ago (Auto-synced today) • Pre-cached in local vault (Instant response • Zero government portal downtime)

Find legal terms confusing?
Toggle our zero-jargon 5th-grade explainer or ask our RERA-grounded AI assistant.

What you should know

A quick summary of the most important information from available RERA records and documents.

Project Registered

Officially registered on Haryana RERA portal

DLF Limited

Registered builder on record (DEV-10003)

30 June 2028

Declared official completion date

Lag: 25%
Physical Work42%
Elapsed Time67%

Project Overview

DLF The Arbour - Sector 63 is recorded under Haryana RERA by DLF Limited, situated in Sector 63, Golf Course Extension Road, Gurugram. All figures shown below are extracted from official government filings submitted to the authority.

Property Type4 BHK Ultra Luxury (3,950 Sq.Ft.)
Total UnitsNot Disclosed on Record (Unverified)
Project Land Area25.71 Acres (1,120,000 sq.ft.)
Current Work StatusWork Going On (42%)
Possession Target30 June 2028
RERA RegistrationRC/REP/HARERA/GGM/671/403/2023/15
Registration Date1 March 2023
Land Title StatusFreehold Land (Clear Search Report by DLF Legal)
Designated Escrow BankState Bank of India

Location Record

Open Google Maps ↗
Resolving Survey Geolocation (Gurugram)...
Gurugram, Haryana
28.4050° N, 77.0850° EGolf course extension
Sector 63, Gurugram, Haryana 122002

Registered Locality: Sector 63, Golf Course Extension Road, District: Gurugram, State: Haryana.

Builder On-Time Record

DL
Alliance Coimbatore Realty Group
100% On-TimePunctual

Tier-1 Institutional Track Record

Filing Status Trail

State RERA Registration
1 March 2023
On Record
Construction Status
Work Going On (42%)
Reported
Target Completion
30 June 2028
Scheduled

The Mismatch Alarm: 4 Brochure vs RERA Discrepancies Audited

Truth Checker Active

We audited potential possession drift, net carpet usable area vs 35% loading, unapproved club extras, and 70% escrow ring-fencing for DLF The Arbour - Sector 63.

70% Escrow Ring-Fencing Audit

RERA Act 2016 • Section 4(2)(l)(D)
Ring-Fenced Account

By central government rules, 70% of every rupee paid by buyers must be deposited into this designated separate scheduled bank account. Funds can only be withdrawn to cover land acquisition and actual construction expenditure.

Designated Bank:State Bank of India
Separate RERA Escrow A/C:•••• 8192
Branch IFSC Code:SBIN••••
Mandatory 3-Tier Withdrawal Certifications
1. ArchitectForm 1 Progress
2. EngineerForm 2 Structure
3. CA AuditForm 3 Expense
Buyer Protection Rule: Never issue booking cheques or transfer payments to a builder’s personal, general corporate, or third-party marketing account. All payments must name this designated separate RERA escrow account.

Cost vs Construction Progress Ratio

Capital Diversion & Overdraw Risk Audit
Certified Metrics

Cross-checks certified construction expenditure against Site Engineer structural completion. Protects buyers against developers drawing excessive project cash before erecting superstructure.

Physical Site Progress:42% Completed
Land Cost₹1.85 Cr28% of outlay
Building Cost₹4.8 Cr72% of outlay
Total Outlay₹6.65 CrForm 3 CA Total
Financial Divergence Risk:Low / In-Sync

Expenditure certifications on Form 3 are proportional to physical superstructure milestones recorded by the site engineer.

Source: Chartered Accountant Form 3 & Engineer Form 2

Carpet Area Transparency & Loading Check

RERA Section 2(k) Usable Area Mandate
Section 4 Protected

Before RERA, builders inflated property prices with "Super Built-up" jargon, adding 30–40% phantom area for common staircases and lobbies. RERA mandates pricing strictly on Net Usable Carpet Area.

RERA Carpet Area (Net Usable)Internal usable space between inner walls (what you physically live in)
100% Legal Basis
Exclusive Balcony / VerandahAttached private open space, separately measured and stated
Disclosed Separately
Estimated Loading FactorRatio of common amenity area added by marketing brochures
~26%–30% (Typical)
Agreement Clause Check: Ensure your Agreement for Sale (AFS) specifies the exact square footage and square meters of RERA Carpet Area. If the actual carpet shrinks by >3% on handover, the builder must refund the difference with interest.

Government Due-Diligence Checklist

6 Critical Checks Before You Commit
6/6 Evaluated

Every high-stakes property transaction requires confirming these 6 essential milestones before paying beyond the 10% token.

1. 30-Year Title Search & Freehold Ownership
Freehold Land (Clear Search Report by DLF Legal)
Verified
2. Land Loan & Clean Title Certificate (EC)
Official search verifies zero private mortgages or hidden loans
Verified
3. Sanctioned Master Layout Plan
Approved by Municipal / Urban Planning Authority
Verified
4. Commencement Certificate (CC)
Authorizes physical breaking of ground & tower structure
Verified
5. Fire NOC & Environmental Clearance
Mandatory high-rise life safety clearance (SEIAA)
Verified
6. CA Form 3 Escrow Audit & Quarterly QPR
Filed on Haryana RERA official portal
Verified
Cross-checked against state registry filings