Back to Builders DirectoryEntity ID:
DEV-10870Registered Developer FirmChronic Delay Risk
UJJAIN DEVELOPMENT AUTHORITY
SECTOR B TRIVENI VIHAR, UJJAIN
Track Record Rating
40%
On-Time Handover RateTotal Projects5
Completed2
Ongoing3
Delayed3
Avg Delay88m
Portfolio Value₹18.29 Cr
Official RERA Evaluation
Escrow & Delivery Analysis
Under Section 4(2)(l)(D) of RERA, 70% of collections from buyers for every project registered by UJJAIN DEVELOPMENT AUTHORITY must be held in a designated scheduled bank escrow account. Before booking in any project by this developer, verify the CA Form 3 withdrawal certificate and confirm whether site progress matches architect declarations.
Certified under State RERA Authorities
Direct government record verification
Project Portfolio
Official filings on recordRegistered RERA Projects (6)
MP-GOV-IND-UUk3WDd1WFWork Going On
DIVYA AUREON - B
Indore (Indore), Indore, Madhya Pradesh
Completion Date:31-12-2025
Check Property Report
MP-GOV-UJJ-ampZVEhZU2Work Going On
CONSTRUCTION OF 25 MIG AT KSHIPRA VIHAR UJJAIN
Ujjain (Ujjain), Ujjain, Madhya Pradesh
Completion Date:24-01-2019
Check Property Report
MP-GOV-UJJ-WlZhOXVtVVReady to Move
CONSTRUCTION OF 15 SR, HOUSES AT TRIVENI VIHAR BLOCK NO. D-7, UJJAIN
Ujjain (Ujjain), Ujjain, Madhya Pradesh
Completion Date:21-11-2021
Check Property Report
MP-GOV-UJJ-M3NobHBzckReady to Move
CONSTRUCTION OF 48 EWS HOUSES AT SECTOR B TRIVENI VIHAR, UJJAIN
Ujjain (Ujjain), Ujjain, Madhya Pradesh
Completion Date:27-04-2019
Check Property Report
MP-GOV-UJJ-LzlDbjlMOGWork Going On
CONSTRUCTION OF 09 SR. MIG HOUSES AT L.P. BHARGAV NAGAR BLOCK NO. - 10 & 16, UJJAIN
Ujjain (Ujjain), Ujjain, Madhya Pradesh
Completion Date:03-10-2019
Check Property Report
MP-GOV-UJJ-a2ZZZjFZZTWork Going On
CONSTRUCTION OF 12 DUPLEX HOUSES AT L.P. BHARGAV NAGAR BLOCK NO. - 1, UJJAIN
Ujjain (Ujjain), Ujjain, Madhya Pradesh
Completion Date:23-05-2019
Check Property Report